A handover package should let the owner occupy, operate, maintain and alter the building with confidence. The exact deliverables come from the contract, approvals and asset operator’s requirements, so agree the list before construction rather than at the final inspection.

What documents are normally needed?

Check the applicable approvals and certificates, commissioning and test records, operation and maintenance manuals, warranties, spare parts, training records, keys and access credentials, defect lists and as-constructed information. Include equipment identifiers and contacts that facilities staff can actually use. Some assets require structured data for the owner’s maintenance system.

How do you check quality?

Use a deliverables register with responsible party, due stage, reviewer and acceptance status. Test a sample: can the operator locate a plant item, understand its settings, find its warranty and identify the isolation point? A folder of unlabelled PDFs is not a usable handover.

Does handover start at practical completion?

No. Plan commissioning, witness testing, operator training and staged delivery of records while systems are being installed. Separate documents required for occupation from those that can be closed during an agreed defects period, subject to the contract and approvals. Keep open items visible.

For example, an air-handling unit may appear in a manual but have no matching asset number on site, no test result and no maintenance contact. A short operator-led sample review while the contractor is still present can expose this early enough to correct the whole dataset.

If a future refurbishment depends on reliable asset records, the handover process is part of project delivery. Read about as-built drawings and COBie data.